Follow the progress of our new school build with the latest news, milestones, and developments.
Current Status
Enabling Works — 19 January to 10 July 2026
Latest News
We are pleased to share the latest progress on our new school build. The project is now in the Enabling Works phase — a 24-week programme running from 19 January to 10 July 2026, preparing the site ahead of the main construction. Below you will find details on the current activities taking place.
Work continues to progress well across the site during the Easter holiday period, with a number of key activities taking place:
We will continue to share updates as work advances over the coming weeks.
Work continues to progress well across the site this week, with all ongoing activities from previous weeks continuing.
We will continue to share updates as work advances over the coming weeks.
Significant progress has been made this week with the demolition of the KSVA building taking place on Tuesday 17 March. Alongside this, several other key works are continuing across the site.
We will continue to share updates as work advances over the coming weeks.
Work continues across multiple areas of the site this week, with a number of visible changes taking shape around the school grounds.
We will continue to share updates as work advances over the coming weeks.
Another busy week on site with several key milestones reached and ongoing works continuing across the school grounds.
We will continue to share updates as work advances over the coming weeks.
We are pleased to share further progress on the new school build, with several key developments taking place across the site as preparations continue for the next phase of construction.
We will continue to share updates as work advances over the coming weeks.
We are pleased to share further progress on the enabling works phase of the new build.
We will continue to share updates as work advances over the coming weeks.
The T4 classroom has been demolished this week as part of the ongoing site clearance. Work has also begun on the back field, with preparation underway to support the next stages of the enabling works programme.
The temporary classroom block E15 has been successfully demolished as part of the ongoing enabling works. This is a key milestone in preparing the site for the new build, freeing up space for the construction programme to progress.
Watch the timelapse of the demolition below:
The first four weeks of the enabling works programme focus on establishing the construction site and carrying out essential preparation works across the school grounds. Key activities during this period include:
We will continue to provide regular updates as the project progresses. For more information about the new school build and the wider programme, visit the Future Wales page.